How long will my project take to build?


Construction can vary from project to project
dependant upon the size, type and complexity of a project. There are also a number of other factors that may also affect the construction schedule. Listed below are some typical projects timeframes as well as a list of factors that could affect the schedule of the projects.

· Interior Bathroom remodel – 30 to 60 days / 1 month to 2 months
A remodel that is working within the existing space of the bathroom
without an enlargement to the room.

· Bathroom Remodel – 45 to 90 days / 1.5 to 3 months
A bathroom remodel where you are expanding into another room involving
opening up walls and then repairing the adjacent room(s)

· Kitchen Remodel –75 to 120 days / 2.5 to 4 months
A complete gutted kitchen remodel working within an existing kitchen space.

· Kitchen Addition and Remodel –100 to 160 days / 3.5 to 5.5 months
A addition to a house to expand and remodel the kitchen.

· Full house remodel –180 days to 365 days / 6 months to 1 year
A project that would completely gut out the interior of the home as well as
include a substantial amount of new exterior work (windows, roof siding etc.).
This will vary quite a bit based on the size of the home.

· Small New House – 150 days to 240 days / 5 to 8 months
1500 square feet to 2500 square feet

· Medium Sized House – 210 days to 300 days / 7 to 10 months
2500 to 3500 square feet

· Large House – 300 days to 420 days / 10 to 14 months
3500 to 5000 square feet

· Larger House – 360 days to 540 days / 12 to 18 months
5000 to 7500 square feet

· Very large House – 18 to 24 months
7500 square feet plus

 